Haryana RERA Orders Raheja Developers to Refund ₹27.98 Lakhs to Homebuyer Over 2.7-Year Project Delay

Raheja Developers has been ordered by Haryana RERA to refund ₹27.98 lakhs to a buyer after failing to deliver the flat in their Raheja Maheshwara project on time.
 
Haryana RERA Orders Raheja Developers to Refund ₹27.98 Lakhs to Homebuyer Over 2.7-Year Project Delay

The Haryana Real Estate Regulatory Authority, RERA, has asked Raheja Developers Limited to return ₹27.98 lakhs along with interest to a homebuyer as the project of Raheja Maheshwara was inordinately delayed. This was the verdict delivered by the RERA bench headed by member Ashok Sangwan.

The complainant had booked a flat in the Raheja Maheshwara project, but the developer failed to deliver the possession within the stipulated time and caused a delay of over 2.7 years. Frustrated with the delay, the homebuyer approached Haryana RERA, seeking a refund of the amount paid, along with applicable interest.

RERA's Order

After considering the case, Haryana RERA has held Raheja Developers liable for not delivering as promised and ordered a refund. The Authority emphasized how such delays affect the confidence and financial stability of homebuyers, making the refund necessary.